PROJECT DESCRIPTION
This was another school project carried out by us. This was also a live site as the school was still open.
Diversions to water sewer and storm drainage all had to be carried out at the weekends.
Asbestos removal was carried out as required on prefabs.
Works included foundations, concrete floors, concrete shuttering, drainage management, water mains installation, footpaths and kerbing.
14 new classrooms were added on and a new gymnasium also.
This site was a little trickier than most as it was live, but we overcame all obstacles and completed the job on time.