PROJECT DESCRIPTION
Enniscorthy Vocational College was a large-scale school construction project with a duration of 2 years. There were 8 men and machinery on site for the duration of this school construction project.
Firstly, there was a reduced level dig requiring soil removal with approximately 3,000 lorry loads of sub-soil being drawn off site to a licensed tip.
Our biggest challenge in this job was diverting existing services that had to be kept live as the school was still open and operating.
Works on this project included foundations, holding down bolts, steel tying, concrete floors, drainage management, water mains, backfill, radon barrier installation, kerbing, footpaths and seating areas.
We were very pleased with the outcome of this project as it went very well.